You are a Project Manager whose projects are integrated with Financial Management System (FMS). TheFMS pushes Actual Costs and Actual Hours to your projects as of the Actual Date.UpdatingPercent complete using the pushed Actual Dates,Actual Costs, and Actual Hours has createdinaccuratepicturesofthe overall%complete, because there are steps withinactivities that clearly have not completed.
Which PercentComplete Typewould be the best selection for activities in this project?
A. Physical
B. Units
C. Effort
D. Duration
Cost Variance is calculated as .
A. Earned Value Cost - Actual Cost
B. the Actual Cost of Work Performed
C. the Budgeted Cost of Work Scheduled
D. Budget at Completion - Earned Value Cost
What is the significance of the setting "Summarize project basedon high level resource planning"?
A. Summarized project data will reflect Top Down plans.
B. Summarized project data will reflect Bottom Up plans.
C. Summarized project data will reflectactualspushed from another application.
D. Summarized project data will be monetized.
What is the significance of the setting "Summarize project based on detailed activity resource assignments"?
A. Summarized project data will reflect Top Down plans.
B. Summarized project data will reflect Bottom Up plans.
C. Summarized project data will reflect integrated Actuals.
D. Summarized project data will be monetized.
What is the highest level of a Work Breakdown Structure (WBS)
A. Enterprise
B. Portfolio
C. Program
D. Project
You received an email from a Portfolio Manager asking you to checkperformance metrics for the past months on each of the projects filtered for that portfolio.You cannot locate the portfolio that the email referenced.
What is probably the reason you cannot find the portfolio?
A. It Is a User Portfolio created by the Portfolio Manager
B. It is a User Filtered Portfolio that hasn't been refreshed.
C. You don't have the appropriate license for the Web.
D. You haven't been assigned as a resource to the projects.
Identify the true statement.
A. The Must Finish By constraint is used as the starting date for the backward pass.
B. The Must Finish By constraint forces all activities In the project to finish by that date.
C. The Must Finish By constraint affects thetotal Role limits for the project.
D. All activities have negative total float without a Must finish By constraint assigned to the project.
You are a Project Manager who ismanaging several projects in Primavera P6 EPPM Web interface.
Identify the valid navigation options for opening a project in the Web interface.
A. In the Personal Workspace/GANTT Chart portlet, double-click the project name.
B. In the Personal Workspace/My Projects, click the project name.
C. In Portfolios/Executive Summary click the project name.
D. In Portfolios/GANTT Chart click the project name.
Identify the impact of deleting a resource from the Resource Breakdown Structure?
A. Allactualand remaining work are removed from the database.
B. Costs for pastprojects would not be affected as theactualhave already been recorded In the database.
C. Budgets for future projects would be removed from the database.
D. Budgets from past projects would be removed from the database.
E. Costs for past projects would be reduced because the cost associated with the resource is deleted.
Issue Codes .
A. can be viewed by all users at all times
B. can have values assigned to them
C. are created in the Risks menu
D. cannot be edited after launch