You have projects and tasks defined with transaction controls, which does not allow certain types of charges to the project. Your business needs to create invoices in AP with this project every period and hence would like to make the process easier by creating a distribution set. As you create the distribution set, you notice that these distribution set lines are not validated against the project transaction controls and you are allowed to save it without any validation errors. Identify the reason why the project transaction controls are not applied. (Choose the best answer.)
A. There is no expenditure type information available on the distribution set line.
B. There is no expenditure organization information available on the distribution set line.
C. There is no expenditure item date information available on the distribution set line.
D. The account code combination is not available on the distribution set line.
Identify the attribute of a project type that determines if expenditure items are billable, and the amount type to be used as the basis for transfer pricing. (Choose the best answer.)
A. work type
B. event type
C. cost type
D. expenditure type
Your customer wants additional project information for detailed account balance maintenance, reconciliation, and reporting. Identify the configuration in subledger accounting that can be set up to fulfill this requirement. (Choose the best answer.)
A. Accounting Method
B. Journal Rules
C. Supporting References
D. Accounting Rule
E. Mapping Sets
You recently made some changes to a project contract and the current status of the contract is Under Amendment. Identify the correct sequence of activities that can take place on that contract. (Choose the best answer.)
A. On Hold > Pending Acceptance > Active
B. On Hold > Pending Approval > Active
C. Pending Approval > Pending Acceptance > Active
D. Pending Acceptance > Pending Approval > Active
What are three configuration items that you need to set up by using the Project Organizations functional area in Project Financial Management configurations? (Choose three.)
A. Manage Project Unit Organizations
B. Mange Business Unit
C. Manage Project Organization Classifications
D. Mange Project Types
E. Manage Project Unit Options
Identify the three contract attributes from Project Performance Data that are used in Project Performance dashboard regions. (Choose three.)
A. Expenditure Type
B. Projects
C. Contract Line
D. Contract Header
E. Task
Identify three correct statements about the integration of Primavera P6 Enterprise Project Portfolio Management and Oracle Project Portfolio Management Cloud. (Choose three.)
A. Event completion flows from Primavera P6 Enterprise Project Portfolio Management to Oracle Project Portfolio Management Cloud.
B. Billing events flow from Primavera P6 Enterprise Project Portfolio Management to Oracle Project Portfolio Management Cloud.
C. Summarized actual quantity and cost flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.
D. Projects and task definitions flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.
E. Project plans and progress flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.
Your customer wants to see how quantity, cost, and revenue amounts are automatically distributed by using Spread Curve. Identify two period options that are available for this purpose. (Choose two.)
A. Calendar Types
B. Project Accounting Periods
C. Accounting Periods
D. PA Calendar
E. PA-GL Periods
Identify two correct role templates available on the Oracle Entitlement Server to generate roles for Project Organization Security. (Choose two.)
A. Project Manager Template for Project Organization Security
B. Project Administrator Template for Project Organization Security
C. Project Creator Template for Project Organization Security
D. Project Accountant Template for Project Organization Security
E. Project Billing Specialist Template for Project Organization Security
As part of maintaining (importing new employees that were added last week) project enterprise labor resources in your organization, you submit the Maintain Project Enterprise Labor Resources process to create and update resources based on changes in HCM. You define maintenance conditions on the Manage Project Enterprise Labor Resource page to process both employees and contingent workers. (Choose the best answer.)
A. Pool Membership
B. attributes that the project enterprise resources are assigned after creation
C. Jobs
D. Person Type