You want to export your project plan to Oracle Project Financial Management Cloud after initial scheduling is complete in Microsoft Projects. Identify three conditions that must be met for exporting milestone tasks. (Choose three.)
A. only one labor resource assignment with 100 effort
B. lowest-level tasks set up with non-zero duration
C. lowest-level tasks set up with zero duration
D. only one labor resource assignment with 0 effort
E. percent work complete values of 0 or 100 percent
Your client has decided to import time cards into Project Costing from Oracle Fusion Time and Labor. They have a requirement to make adjustments to time card entries whenever needed.
In which work area will the employees and contingent workers be able to modify their time cards?
A. Both Time and Cost
B. Cost
C. Asset
D. Time
Which component of performance measures allows you to select the method that is used to measure accounts such as budget, forecast, and actual?
A. Accounts Member
B. Time Member
C. Category Member
D. Scenario Member
Your organization has been using project class categories and codes for reporting purposes and is set up at the project level. You recently defined a new project type, Capital-Contract, and created new class categories named Build, Operate, and Transfer (BOT) and Build, Transfer, and Maintain (BTM), with class codes of Yes/No. But on creation of a project, you are unable to associate these class categories and codes.
Identify two setups that are mandatory for these class categories and codes to be displayed. (Choose two.)
A. Class codes should be associated with a related set code.
B. Class categories should be assigned to business unit.
C. Class categories should be assigned to project type.
D. Class codes should be assigned to project unit.
Which application would you use to map application roles to external roles? (Choose the best answer.)
A. Oracle Identify Manager
B. Authorization Policy Manager
C. BPM Work List
D. Security Console
You configure one OTBI using Project Cross Subject Area Analysis Real Time. You notice that all measures (Budget, Forecast, Cost, Commitments, Revenue, and Invoice) are not available for Bill-To-Customer and Contract and Contract Line dimensions. Identify the reason for this behavior. (Choose the best answer.)
A. The Bill-To-Customer dimension applies only to Invoice measures, but the Contract and Contract Line dimensions do not apply to Revenue and Invoice measures.
B. The Bill-To-Customer dimension applies only to Revenue and Invoice measures.
C. The Contract and Contract Line dimensions apply only to Invoice measures.
D. The Bill-To-Customer dimension applies to Invoice measures, and the Contract and Contract Line dimensions apply to Revenue and Invoice measures.
E. The Bill-To-Customer dimension does not apply to Invoice measures, but the Contract and Contract Line dimensions apply only to Revenue and Invoice measures.
Which two statements are true about the borrowed and lent cross charge method? (Choose two.)
A. Internal Invoice is not generated with this method.
B. This method allows you to process cross charge transactions across legal entities.
C. This method creates accounting entries that move an amount equal to the transfer price between the provider and receiver organizations
D. You must set up a contract business unit to use this method.
Your organization has been awarded a new contract based on which you are allowed to sell:
Items not tracked in inventory Inventory items Services
Which contract structure would fulfill your requirement of item sales? (Choose the best answer.)
A. Create two contract lines with a line type each of "free-form, project-based buy agreement" and "bundle sell, project-based".
B. Create two contract lines with a line type each of "sell intent, free-form, project-based " and "sell intent, item, project-based".
C. Create two contract lines with a line type each of "product, project-based, sell agreement, standalone" and "sell intent, item, project-based".
D. Create two contract lines with a line type each of "sell intent, item, project-based' and "subscription, project-based, sell".
Your organization wants to capture the project details for work order labor and equipment resource transactions as part of a project-driven supply chain solution.
Which expenditure type class is recommended for the expenditure types that need to be defined for these type of transactions?
A. Supplier Invoice
B. Work In Process
C. Usages
D. Inventory
Your organization has a requirement to send notifications to the owners of the associated tasks when the status of a deliverable is set to Complete. You have been asked to evaluate generate public events for project deliverable status changes feature to manage this requirement.
Which two statements are true about this feature? (Choose two.)
A. The public event is not generated when the priority of a deliverable changes.
B. The public event is not generated when a deliverable is created or deleted.
C. The public event is generated when a deliverable is created or deleted.
D. The public event is generated when the progress status for a deliverable changes.