In a manufacturing plant, the work definition and rate plans of Material, Resource, and Overhead of an assembly have been defined as required. A cost accountant created different scenarios to represent different manufacturing and cost assumptions and compare the results. When the cost assumptions are finalized, the cost accountant is expected to publish the cost scenario to cost accounting. Identify three process steps that the cost accountant has to perform to transfer the assembly to cost accounting in frozen type.
A. Publish cost planning scenario to Accounting.
B. Build cost planning scenario and perform cost roll up.
C. Create Accounting Distributions.
D. Transfer transactions from production to Costing.
E. Define a cost planning scenario with Material, Resource, Overhead cost plans, and work definition.
F. Transfer Transactions from Inventory to Costing.
To reduce the subassembly stock with no impact on material planning of child components of the
subassemblies stock, you need to modify the multilevel item structure of a product.
Identify the action that meets this requirement.
A. Change the Supply Type = Push in Item definition and Work Definition, for subassemblies having high inventory stock.
B. Change the Supply Type = Phantom in Item definition and Work Definition, for subassemblies having high inventory stock.
C. Change the Supply Type = Assembly Pull in Item definition and Work Definition, for subassemblies having high inventory stock.
D. Change the Supply Type = Operation Pull in Item definition and Work Definition, for subassemblies having high inventory stock.
The Manufacturing plant has two 8-hour shifts for the work center WC1: Day Shift and Night Shift. You associate four units each for resources R1, R2, R3, and R4 to the work center WC1. The customer wants to assign all units of resource R2 available for Day and Night Shift. Identify the correct sequence of steps to achieve this requirement.
A. Associate Resource R2 with Work Center WC1> Select Available 24 Hours check box> Resource Availability region> Enter 4 in Day Shift Column> Enter 4 in Night Shift Column.
B. Associate Resource R2 with Work Center WC1> Deselect the Available 24 Hours check box> Resource Availability region> Enter 2 in Day Shift Column> Enter 2 in Night Shift Column
C. Associate Resource R2 with Work Center WC1> Select the Available 24 Hours check box> Resource Availability region> Enter 2 in Day Shift Column > Enter 2 in Night Shift Column.
D. Associate Resource R2 with Work Center WC1> Deselect the Available 24 Hours check box> Resource Availability region> Enter 4 in Day Shift Column> Enter 4 in Night Shift Column.
Identify four parameters that are considered in the calculation of manufacturing lead time in Oracle Manufacturing Cloud.
A. Resource calendars of the work centers involved
B. The primary work definition of the item
C. The lot size of the item
D. The shifts are defined in the plant calendar
E. Plant calendar exceptions
F. Resource calendar exceptions
You want to use a predefined Standard Operation in a Work Definition, but you also want to change the usage of the Standard Operation resource. Identify the setup required.
A. Deselect the Referenced check box while adding the standard operation to the work definition and change the usage manually.
B. Select the Referenced check box while adding the standard operation to the work definition and change the usage manually.
C. Use the Transfer and Edit Standard Operation functionality to edit the resource usage.
D. Use a Resource exception for the resource and alter its usage.
Planning Central has collected manufacturing data for a Work Order WO-2045 (Make Item AS1000), where actual duration of work order is 2 days. Item AS1000 manufacturing lead time is 1.25 days. A plan is run and the Work Order WO-2045 is rescheduled. Identify the duration of the rescheduled Work Order WO- 2045.
A. Rescheduled Work Order WO-2045 duration = 2 days
B. Rescheduled Work Order WO-2045 duration = 1.25 days
C. Rescheduled Work Order WO-2045 duration = 3.25days
D. Rescheduled Work Order WO-2045 duration = 0.75 days
Identify the two capabilities that the Application Development Framework Desktop Integration (ADFDI) framework provides for Work Definitions in Manufacturing Cloud.
A. You can mass create and update work definitions and their operations, items, and resources.
B. You can mass create and update work definitions and their operations, items only and cannot add resources in work definitions.
C. You can mass create and update work definitions and their operations only and cannot add items and resources in work definitions.
D. You can copy work definitions form one organization to another organization.
A Production Supervisor queries a Work Order (WO-1025) from the manage Work Orders page. On the
Entering Edit Work Order: WO-1025 page, he finds General Information, Operations and History tab, but
not the Reservations tab.
Identify the two reasons that can cause the Reservations tab not to be displayed.
A. Work Order (WO-1025) is not a Configured item Work Order.
B. Work Order (WO-1025) is not a Back-to-Back Work Order.
C. Work Order (WO-1025) is not a Drop-Ship Work Order.
D. Work Order (WO-1025) is not a Pick-to-order Work Order.
E. Work Order (WO-1025) is not a Plan-to-produce Work Order.
The Cost Accountant has reported to the Production Supervisor that the Work Order transactions are not
getting transferred to Costing.
Identify the reason for work order transactions not getting transferred to Costing.
A. The Manage Item Rules setup is not complete.
B. The Costing Interfaced Attribute is enabled in the resource definition.
C. The item was made inactive after the Work Order transaction.
D. The Costing Interfaced Attribute is not enabled in the resource definition.
Your customer has completed the required setup steps for automatic work definition. Identify the option that shows the navigation steps needed to create an automatic work definition.
A. Manufacturing > Work Definition> Manage Work Definitions> Actions> Create automatic work definition
B. Product Management> Product Information Management> Items> Edit Item > Actions> Create automatic work definition
C. Manufacturing> Work Definition> Manage Standard Operations> Select default standard operation> Actions> Create automatic work definition
D. Manufacturing > Work Definition> Manage Standard Operations> Create automatic definition