Identify the missing word(s) in the following sentence, PRINCE2 recommends three levels of [?] to reflect the needs of the different levels of management involved in a project.
A. Management strategies
B. Plan
C. Stakeholder interests
D. Time-driven controls
Which is a type of issue?
A. A lesson
B. A request for change
C. An Exception Report
D. A risk with an estimated high impact
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
A. Directing a Project
B. Managing a Stage Boundary
C. Controlling a Stage
D. Starting up a Project
Identify the missing words in the following sentence. The purpose of the Starting up a Project process is as much about [?] as it is about requesting authorization to initiate viable projects,
A. producing an achievable Project Plan
B. preventing poorly-conceived projects from ever being initiated
C. obtaining approval from all stakeholders
D. setting up the required project controls
Which role is responsible for specifying the project benefits?
A. Corporate or programme management
B. Executive
C. Senior User(s)
D. Project Manager
Which is an objective of the Controlling a Stage process?
A. Prepare a Stage Plan for the next stage
B. Obtain approvals for completed products
C. Prevent scope creep' by monitoring products for uncontrolled change
D. Make arrangements to address all open issues and risks, with follow-on action recommendations
Which is a purpose of a Risk Register?
A. Capture risks that may occur during the project
B. Record how risk management activities will be undertaken on the project
C. Record the risk tolerance for the project
D. Capture issues which are impacting on the delivery of the project objectives
Which is NOT included in the PRINCE2 definition of a project?
A. A project is a temporary organization
B. A project's purpose is to deliver one or more business products
C. A project is part ofbusiness as usual
Identify the missing word(s) in the following sentence. Quality assurance provides assurance to the [?] that the project is being conducted appropriately whilst Project Assurance provides the same assurance to all the project's stakeholders.
A. Project Manager
B. Executive
C. corporate or programme management organization
D. D. Supplier groups
If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?
A. Checkpoint Report
B. Highlight Report
C. Issue Report
D. Product Status Account