Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?
A. Mandatory
B. Discretionary
C. Internal
D. External
Which tool or technique is required in order to determine the project budget?
A. Cost of quality
B. Historical relationships
C. Project management software
D. Forecasting
Which of the following is a narrative description of products, services, or results to be delivered by a project?
A. Project statement of work
B. Business case
C. Accepted deliverable
D. Work performance information
Which of the following project documents is an input to the Control Scope process?
A. Vendor risk assessment diagram
B. Risk register
C. Requirements traceability matrix
D. Area of responsibility summary
Another name for an Ishikawa diagram is:
A. cause and effect diagram.
B. control chart.
C. flowchart.
D. histogram.
Which is an output of the Collect Requirements process?
A. Requirements traceability matrix
B. Project scope statement
C. WBS dictionary
D. Work performance measurements
Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:
A. manager.
B. success.
C. deadline.
D. scope.
The cost benefit analysis tool is used for creating:
A. Pareto charts.
B. quality metrics.
C. change requests,
D. Ishikawa diagrams.
Which of the following is an output of the Information Distribution Process?
A. Project calendar
B. Communication management plan
C. Requested changes
D. Communication requirement plan
What is the tool and technique used to request seller responses?
A. Procurement documents
B. Expert judgment
C. Bidder conferences
D. Contract types