Beth is the project manager for her organization. Her current project has many deliverables that have been defined at a high level, but the details of the deliverables are still unknown. In her project, Beth is planning in detail only the activities that are most imminent in the project work. This approach to project management planning is known as what?
A. Imminent activity management
B. Rolling wave planning
C. Predecessor-only diagramming
D. Decomposition
You work as a project manager for BlueWell Inc. There have been changes to the project scope in your project. These changes will cause the project schedule to change as well, so you will need to update the schedule and the schedule baseline. The schedule baseline is a component of what?
A. Project calendar
B. Project constraints
C. Project objectives
D. Project management plan
You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You review these activities with your project team discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You decide on to create a new schedule for the project. What project management process are you working with when you create a new target schedule?
A. Estimate activity durations
B. Estimate activity resources
C. Control schedule
D. Develop schedule
You are the project manager for the NHQ Project. Management has asked you to create a time estimate for this project although you have only just received the project charter. They would like some idea of how long the project will take based on the information in the project charter. While you are uncomfortable giving any type of estimate at this point, you work with your assigned project to create a quick time estimate. What type of estimate have you created for management?
A. Analogous estimate
B. Broad estimate
C. Rough order of magnitude
D. Expert judgment
Vicky is the project sponsor of Robert's project. She has requested several changes for the project scope and these changes have, of course, been approved. Robert needs to incorporate the project scope changes into the activity list. Where else should Robert reflect these project changes?
A. Project final report
B. Scope baseline
C. Quality control mechanism
D. Cost baseline
You're a project manager and you've completed your project schedule. The schedule will take 18 months to complete the project work. Throughout the schedule there are instances that the project work will require the project team members to work more than fifty hours per week. If you must adhere to a maximum of 45 hours of project work per team member, per week, what will likely happen to your project schedule as it stands right now?
A. Nothing, the 45 hours limit is a guideline.
B. The project will take longer to complete.
C. The project will take less time to complete.
D. The project will require more resources.
Yolanda is the project manager for her organization. She is creating a performance report for her sponsor. Typically, the performance report includes all of the following factors except for which one?
A. Current status of risk and issues
B. Quality control activities
C. Analysis of past performance
D. Work to be completed next
Complete this sentence:
_________________________ is the process of collecting and distributing performance information including status reports, progress measurements, and forecasts.
A. Corrective action
B. Report performance
C. Earned value management
D. Monitor and control project performance
You are the project manager for the NHQ project. The management has reminded you that you must not allocate any project team member for more than 25 hours per work week on your project. This policy is because your organization is in a weak matrix and the project team members are on several projects at once within the organization. The 25-hour limit per resource is an example of which one of the following?
A. Expert judgment
B. Enterprise environmental factor
C. Resource limitation
D. Organizational process asset
You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You reviewed these activities with your project team and discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You elect to create a new schedule for the project. What project Management process are you working with when you create a new target schedule?
A. Develop schedule
B. Estimate activity durations
C. Control schedule
D. Estimate activity resources