What was the original planned duration for Activity A through Activity G?

A. 26.
B. 28.
C. 24.
D. 25.
Which of the following are NOT normally included in the project scope statement, either directly or by reference?
A. Project objectives in terms of cost, schedule and quality measures
B. Project contract between the contractor and owner
C. Project justification
D. Project deliverables
Activity C is a
A. Contentious activity.
B. Continuous activity.
C. 1-day activity.
D. Milestone.
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?
A. The schedule has too much detail to reflect an accurate critical path.
B. Different calendars are assigned to certain activities in the logical chain.
C. The schedule is projecting an "early completion".
D. Certain activities in the critical path have no successors.
Budgeted cost of work scheduled is _______________________.
A. The value of the completed work expressed in terms of the budget assigned to that work
B. The total authorized budget for accomplishing the project scope
C. The expected total cost of an activity, group of activities or the project
D. The sum of all budgets for work scheduled to be accomplished within a given time period
How much Total Float does drafting the product manual have?

A. 15 workdays.
B. 0 workdays.
C. 10 workdays.
D. 5 workdays.
As a change to the network for the current update, activity 6002 is required to begin ten days after the beginning of activity 6001. Which is the simplest logic organization?
A. A start-to-start relationship with a ten-day lag assigned to activity 6001; activity 6002 will be dependent on activity 6001
B. A start-to-start to relationship for both activities 6001 and 6002 with a ten-day lag assigned to activity 6002.
C. A start-to-finish relationship with both activities 6001 and 6002 having a ten-day lag
D. A finish-to-start relationship with a ten-day lag assigned to activity 6002; activity 6001 will be dependent on activity 6002
Determine the correct formula and date for the late start for Activity 9001.
A. The early finish is required in order to determine the answer.
B. LS.6001 Dur.6001 -> 11-20-02.
C. There is insufficient data provided to calculate the answer.
D. LF.9001 Dur.9001 -> 11-20-02.
If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity
A. Is a milestone.
B. It is on the critical path.
C. Was completed in the past.
D. Has yet to be completed.
What is a key first step in developing a critical path method schedule?
A. Drawing a bar chart of the key phrases of the work.
B. Defining the execution plan to meet the required scope of work.
C. Setting out the resource to be used and its limitations.
D. Drawing the logic diagram.