A maintenance planner is in the process of planning time sensitive emergency maintenance work orders for a number of assets where items need to be reserved.
What reservation type should be used?
A. Soft
B. Hard
C. Urgent
D. Critical
A company has a requirement that certain GL Accounts expire. In which application can this be defined?
A. Financial Periods
B. Cost Management
C. Chart of Accounts
D. Database Configuration
The business analyst for the purchasing department of a company is creating a workflow process for purchase requisitions. A requirement is to branch the process to different approval groups based on a cost evaluation.
Which method is used to implement this in Workflow Designer?
A. A condition node with an expression.
B. A manual input with a custom action list.
C. An interaction node to review the PR lines.
D. A call out to the purchasing thresholds of the roles.
A rotating asset has been inspected and approved. The asset is then found to be faulty and needs to be returned to the vendor.
What will happen to the asset after it has been returned? (Choose two.)
A. Asset status will change to DECOMMISSIONED.
B. Asset record will be deleted after it has been returned.
C. Returned to Vendor checkbox has been selected and made read-only.
D. Asset status will change to INACTIVE when there is no inventory balance.
E. Asset will be changed to a non-rotating asset and no longer reside in the storeroom.
A storeroom clerk is processing items to be shipped to various locations. In the Inventory Usage application, while processing one of these items, the Split Usage Quantity dialog is displayed and the clerk selects the Auto-Split option.
What is validated?
A. A rotating item is requested and the quantity is more than one.
B. The inventory balance for the item is greater than the ordered quantity.
C. A lotted item with the same quantity has been selected on another usage line.
D. The quantity in a storage bin already meets the required quantity on the Inventory Usage line.
A company has a work order with 50 separate tasks and 40 of the tasks have been completed. The company would like the remaining 10 tasks grouped with a new parent work order.
Which option will group the tasks?
A. Select the task work orders and Create Work Package.
B. Select the task work orders Create Job Plan from Work Plan.
C. Create a new work order and add the task work orders on the Plans tab.
D. Create a new work order and add the child work orders on the Plans tab.
Which application must be used to create services that can be selected from a value list on a purchase order?
A. Service Items
B. Service Records
C. Common Services
D. Standard Services
A company has acquired a contract for an asset covering labor, materials and tools. What must be created to capture this information?
A. A Master Contract
B. A Warranty Contract
C. A Purchase Contract
D. A Labor Rate Contract
A company wishes to apply an item assembly structure to a location. Which field on the location record is required for this to take place?
A. Asset
B. Spare Parts
C. Rotating Item
D. Hierarchical System
A company has multiple crews that work different days and hours. The administrator must define these work schedules. Where can this be done?
A. Crew Definition in the Labor application
B. Define/Apply Shifts in the Crews application
C. Crew Definition in the Calendars application
D. Define/Apply Shifts in the Calendars application