What is the most granular level of the methodology you can view in the Roadmap Viewer? Please choose
the correct answer.
Response:
A. Scenario
B. Task
C. Deliverables
D. Phase
According to the Definition of Done, which activity must be completed for each sprint? Please choose the
correct answer.
Response:
A. End user training must be delivered
B. Solution must be built and configured in the development system (DEV)
C. Functionality must be tested in the Quality system (QAS)
D. Functionality must be released to the business
What do you do during Sprint Execution? Please choose the correct answer. Response:
A. End a sprint when the sprint backlog items are all complete
B. Measure the sprint progress with a percentage complete report
C. Hold a retrospective at the end of each week
D. Present status of selected user stories in the sprint scope on a scrumboard
What is the purpose of the SAP Activate Methodology?
Please choose the correct answer.
Response:
A. To enable access to the SAP ecosystem
B. To accelerate the initial implementation of SAP S/4HANA
C. To provide end-to-end integrated application lifecycle management
D. To manage project and solution documentation
In which phase of the SAP Activate methodology does the team complete the Transformation Planning?
Please choose the correct answer.
Response:
A. Deploy
B. Explore
C. Prepare
D. Realize
What are the benefits of the SAP best practices? There are 3 correct answers to this question. Response:
A. Fast time to value
B. Predictable results
C. Simple on-boarding to cloud
D. Fixed organizational structure
E. Reduced functional scope
How are the build and test tasks planned and executed in the Realize phase? Please choose the correct
answer.
Response:
A. By using the sprint backlog list as input for each iteration.
B. By executing regression tests after each iteration
C. With Q-Gates for sign off after each iteration
D. By using incremental build in fixed-scope iteration
Who determines the tasks that are required to complete the committed backlog items in a sprint? Please
choose the correct answer.
Response:
A. Project Manager
B. Product Owner
C. Project Team
D. SCRUM Master
In which phase do you verify that the SAP Best Practice solution scenarios meet the business needs of the
customer?
Please choose the correct answer. Response:
A. Explore
B. Deploy
C. Realize
D. Prepare
What do you do during an iterative approach to build a solution? Please choose the correct answer. Response:
A. Build the solution module by module
B. Deliver a prototype of the solution
C. Provide a working solution only at the end of the release
D. Include frequent inspection check-points