Where can you define a network as "header-account-assigned" or "activity-account-assigned"?
A. Network profile
B. Project profile
C. Parameters for the network type
D. Network type
How are earliest dates and latest dates of activities scheduled?
A. Earliest dates are scheduled by backward scheduling, and latest dates by copying the earliest dates
B. Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling
C. Earliest dates and latest dates are scheduled by forward scheduling
D. Earliest dates are scheduled by backward scheduling, and latest dates by forward scheduling
Material
How can the system activate requirements (such as reservations or purchase requisitions)?
Note: There are 2 correct answers to this question
A. Immediately, by saving the project
B. Automatically, using the requirement date and the replenishment lead time
C. Using a standard milestone activity
D. When releasing a network or an activity
Where do you maintain the length of the project ID?
A. Special characters
B. Project coding mask
C. Project profile
D. Project type
Which of the following statements are true? Choose the correct answers. There are 2 correct answers to this question.
A. You can map a project using only one WBS or one network.
B. You can also represent a project using a WBS and one or more networks.
C. You can create a project based on a Activity.
D. You cannot use the characteristics of both the structures (WBS and Networks) together to represent a project.
Which of the following statements apply to project versions? Note: There are 2 correct answers to this question
A. Project versions can be changed
B. Project versions are mandatory for Milestone Trend Analysis (MTA)
C. Project versions can be created automatically based on user status
D. Manually Created project versions always require a project version profile
Project Structures
Which the following statement regarding networks are correct?. Note : there are 3 correct answers for this question.
A. If a network activity requires more capacity than available in a work center, the system automatically proposes an alternative work center.
B. You can assign more than one activity element to a network activity.
C. Capacity requirements of a network activity are reduced when the activity is confirmed.
D. During scheduling, the system plans the network activities in such a way that the assigned work center are not overloaded in terms of capacity.
E. You can assign the same work center to more than one activity on the same network.
A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take to solve the problem?
A. Activate availability control for the WBS elements. Define the tolerance limits on each WBS element
B. Activate availability control in the assigned budget profile. Define the tolerance limits in customizing
C. Activate commitment management in the project definition Enter the budget in the master data of the top WBS element
D. Activate availability control for projects in the controlling area. Enter the plan data for each WBS element
You want to use billing for a customer project. Which customizing object controls the billing of sales order items?
A. Requirements type
B. Requirements class
C. Item category
D. Schedule line category
What are valid procurement types for stock items? Note: There are 3 correct answers to this question
A. Preliminary purchase requisition for WBS element
B. Planned order
C. Third-party order
D. Purchase requisition and Reservation for WBS element
E. Reservation for WBS element