How can you update the degree of processing for an activity?
A. By using results analysis
B. By changing the activity
C. By scheduling the activity
D. By confirming the activity
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct answers to this question
A. The materials must allow sales order or project stock
B. The exact lot size procedure must be used
C. The procurement type of the material must be internal
D. An MRP group must be assigned
Which of the following business processes do NOT lead to the booking of actual costs to an object? Note: There are2 correct answers to this question
A. Goods receipt into unvaluated project stock
B. Recording of external services in the service entry sheet
C. Goods receipt of a non-stock item
D. Goods receipt into valuated project stock
How can you search in the structure overview based on the user status? Note: There are 2 correct answers to this question
A. By searching for the status profile
B. By searching via status selection profile
C. By searching via status combination code
D. By searching for the individual status
Float time is calculated during scheduling.
Which of the following statements about float time are correct?
Note: There are 3 correct answers to this question
A. Float time can be negative
B. Activities with the time constraint "Must start on" always have a negative float time
C. The float time of WBS elements is calculated by extrapolation
D. By default, critical activities have a float time, which is less than or equal to zero
E. The maximum size of a free float is as large as the total float of an activity
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component ?
A. Set up the requirement date aligned with the activity finish date and an offset of 15 days.
B. Set up the requirement date manually as February 5.
C. Set up the requirement date aligned with the activity start date and an offset of 5 days
D. Set up the requirement date aligned with the activity start date and a negative offset of 5 days
Cost and Budget
What function are available for period end-closing in the project System?
A. Result analysis
B. Progress analysis
C. Milestone trend analysis
D. Settl ement
E. Confirmation
You have saved a network and activates with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out" What could be the reason for this error message?
A. Missing budget for material components
B. Missing reservations for material components
C. Missing material availability
D. Missing authorizations to release material components
Which sets of dates can be used to schedule networks? Note: There are 2 correct answers to this question
A. Basic dates
B. Forecast dates
C. Baseline dates
D. Planned dates
Which object is relevant in assembly processing to create an assembly order for the SD document?
A. Project profile
B. Item category
C. Requirement class
D. Control key