Which of the following statements are correct regarding a cross-plant planning scenario?
A. Multiple planning plants are assigned to a maintenance plant.
B. Multiple maintenance plants are assigned to aplanning plant.
C. It is not supported in SAP S/4HANA.
D. It combines maintenance plants in different controlling areas.
Which steps are available for the maintenance technician when using the Report Malfunction tile? Note: There are 3 correct answersto this question.
A. Select and print the maintenance order shop papers.
B. Display the current location of the technical object.
C. Add a URL to provide further information.
D. View details of the technical object by navigating to the Asset Viewer.
E. Input estimated costs for repair malfunction.
Which activities canthe planner perform by using the Maintenance Planning Overview app with the default filters? Note:There are 3 correct answers to this question.
A. Display approved purchase requisitions for which purchase orders have been generated.
B. Display approved purchase requisitions for which NO purchase orders have been generated.
C. Analyze maintenance orders that are still in planning andhave NOT been released.
D. Analyze overdue maintenance orders that have NOT been finally confirmed.
E. Analyze confirmed maintenance orders that have NOT been settled.
Which functionalities are available in the SAP Asset Manager fora maintenance worker? Note: There are 2 correct answers to this question.
A. Display maps. Display and maintain technical objects
B. Change BOM. Create a work orderon the ESRI map
C. Schedule resources. Change task list
D. Confirm time sheets. Attach documents
In which maintenance object can you use an activity type? Note:There are 2 correct answers to this question.
A. Maintenance order operation
B. Maintenanceorder header
C. Notification activity
D. Work center
You want to set up a scenario for regular maintenance. The first event should take place after 1 year; after that, it is a regular cycle of 6 months.Which parameter do you have to use to map this in thesystem?
A. Shift factor
B. Maintenance plan category
C. Maintenance package offset
D. Scheduling indicator
Which statements about the structure indicator are correct? Note:There are 2 correct answers to this question.
A. It defines the allowed characters for a functional location.
B. It can have a maximum length of 50 characters.
C. It defines hierarchy levels of the functional location structure.
D. It defines which data is transferred to the lower levels of the hierarchy.
You require stock material to carry out maintenance tasks. Whichof the following statementsregarding material planning in the maintenance order are correct? Note: There are 3 correct answers to this question.
A. Material can be assigned at order header level.
B. A control key for internal workforce is required when assigning stock material to anorder operation.
C. Material can be assigned at order operation level.
D. The pick list for materials can be printed before order release.
E. A goods receipt can be entered for a technically completed maintenance order.
The planner adds stock materials in the maintenance order. Whichstatements regarding reservations in maintenance orders are correct? Note: There are 2 correct answers to this question.
A. Open reservations can be cleared when a maintenance order operation is finally confirmed.
B. For the combination of order type and planner group you can decide when reservations are created.
C. All open reservations are closed when the maintenance order isset to TECO.
D. Reservations are created only after a material availability checkhas been performed.
What does a virtual data model provides?
A. A copy of the database optimized for analytical purpose
B. Ready to use business reports
C. consumption ready views of data