Which is the minimum role that has access to the Project Administration > Settings > Preferences-Project module?
A. it_project_manager
B. it_pps_admin
C. sys_admin
D. it_program_manager
When creating a project from demand, what related records are moved and copied upon Project Creation?
A. Resource Plan and Cost Plan.
B. Resource Plan and Change Requests.
C. Cost Plan and Assessment.
D. Idea and Demand.
What is a data copy of the current project's task, schedule, or structure that can be used for comparison reporting later?
A. Accrual
B. Forecast
C. Commitment
D. Baseline