When viewing the Resource Usage Profile using the date interval of Week/Day1, resource a being displayed only on Sundays for every resource being analyzed.
Why are all of the resource allocations being displayed on the same day of the week rather than across the dayswhen they are scheduled to occur?
A. All resources are assigned to the project's default calendar, and have been over allocated to other projects.
B. The resource calendar assigned to the resources was deleted by the System Administrator.
C. On the General tab. In the Admin Preferences dialog box, the first day of the week field is set to Sunday.
D. On the Resource Analysis tab, in the User Preferences dialog box, the "Interval for time- distributed resources calculations" fieldisset to "week."
Select the statement that best describes "Manage Scenarios" functionality.
A. You can create a portfolio for your own use or for sharing with other users.
B. You can view portfolio data in different forms.
C. You can capture a snapshot of project data at a specific moment in time.
D. You can select a portfolio to work with or execute commands in the Action bar.
In your project, cost and work effort is not subject to change.
Which duration type should beused?
A. Fixed Units
B. Fixed Duration and Units/Time
C. Fixed Units/Time
D. Fixed Duration and Units