Where are risk response plans captured?
A. In the Risk Scoring Matrix
B. In the Activity Notebook for Risk
C. In the Risk Register
D. In the Project Notebook for Risk
You are a project manager with a required monthly update cycle. You have marked actual start and actual finish dates for your Physical % complete activities, with % complete calculated from activity steps. You schedule and summarize your project plans. However, your activities are not showing 100% complete. What is the problem?
A. Your security does not allow you to update Activity Status.
B. You did not save the changes made to the activities.
C. You have not completed each of the activity steps.
D. You must refresh the view in the web to view the changes.
You are creating a new portfolio scenario. You are attempting to save it for all users, but the selection is unavailable (grayed out).
What is the cause?
A. You have insufficient global security privileges.
B. You have Insufficient project security privileges.
C. You have insufficient portfolio security privileges.
D. You have insufficient user security privileges.