Why does the Product Owner want the Developers to adhere to its Definition of Done?
(choose the best answer)
A. To predict the team's productivity over time.
B. To have complete transparency into what has been done at the end of each Sprint.
C. To know what the team will deliver over the next three Sprints.
D. To be able to reprimand the team when they do not meet their velocity goal for the Sprint.
How much of the Sprint Backlog must be defined during the Sprint Planning event?
(choose the best answer)
A. Just enough to understand design and architectural implications.
B. Enough so the Developers can create their forecast of what work they can do.
C. The entire Sprint Backlog must be identified and estimated by the end of Sprint Planning.
D. Just enough tasks for the Scrum Master to be confident in the Developers' understanding of the Sprint.
What are two effective ways for a Scrum Team to ensure security concerns are satisfied? (choose the best two answers)
A. Add security concerns to the Definition of Done.
B. Delegate the work to the security department.
C. Have the Scrum Team create Product Backlog items for each concern.
D. Add a Sprint to specifically resolve all security concerns.
E. Postpone the work until a specialist can perform a security audit and create a list of security-related Product Backlog items.