Want to pass your Associate in Project Management (APM) APM-001 exam in the very first attempt? Try Pass2lead! It is equally effective for both starters and IT professionals.
VCE
An output of the Create WBS process is:
A. Scope baseline.
B. Project scope statement.
C. Organizational process assets.
D. Requirements traceability matrix.
Which cost estimate technique includes contingencies to account for cost uncertainty?
A. Vendor bid analysis
B. Three-point estimates
C. Parametric estimating
D. Reserve analysis
While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?
A. Communications management plan
B. Human resource plan
C. Quality management plan
D. Procurement management plan