Stakeholders ask the program manager to assess reasons for the project's delay and provide a report. Also, the program manager must identify steps to be taken to ensure the program will finish on time and within budget. The program manager distributes information in accordance with which of the following?
A. Stakeholder engagement plan
B. Program governance charter
C. Schedule management plan
D. Communications management plan
A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited interest in the benefits being produced. The client is only focused on benefits.
Which of the following actions should the program manager take?
A. Focus on the internal stakeholders to ensure cost and schedule objectives are achieved.
B. Balance stakeholder needs through the use of trade-offs among the stakeholder groups.
C. Focus on the external stakeholders to ensure the intended benefits are achieved.
D. Conduct a stakeholder meeting to allow everyone to state their priorities.
One of the constituent project managers asks a new program manager to obtain approval for an additional key project requirement. A tolerance range is set. If the tolerance range is too narrow on a program, what effect will multiple minor changes have on the program?
A. Reduction in program quality
B. Degradation of program communications
C. Reduction in program risk
D. Slow down in program implementation